Learn about the bid packages for the Care Pavillion project. Download meeting presentations and attendee lists.

PROJECT
KICK-OFF MEETING

OCTOBER 6, 2022

PRE-PROPOSAL MEETINGS

 BID PACK #3

JANUARY 10, 2023

BID PACK #4

JUNE 8, 2023

BID PACKAGES

Bid Package
Release Date
Scope
Awarded
#1
October 2022
DIRTT Walls
The Berg Group
#2
October 2022
Mechanical/ Plumbing
Harris
#2
October 2022
Electrical
Parsons
#3
January 2023
Earthwork
Bolander
#3
January 2023
Curtainwall
Empirehouse
#4
June 2023
Concrete (ready mix supply, rebar supply, PT supply, rebar install, forming, pumping)
TBD
#4
June 2023
Waterproofing
RAM Construction Services
#4
June 2023
Rebar Supply
CMC Steel Fabricators
#4
June 2023
Rebar Install
Woody’s Rebar
#4
June 2023
Metal Panel/Terracotta
MG McGrath
#4
June 2023
Fire Protection
Viking Automatic Sprinkler
#5
August 2023
Remaining Enclosure
TBD
#5
August 2023
Structure
TBD
#5
August 2023
Roofing
TBD
#6
October 2023
Drywall
TBD
#6
October 2023
Finishes
TBD
#6
October 2023
Site Improvements
TBD